(resent; there was some list error so it was not processed correctly - Lars)

Attached you can find a short status report from our pipe lay in Skibotn, before the video meeting tomorrow.

Slide 1:
The first slide shows where we are right now, and you can see the excavator close to outrigger W2. During this week everything that can be done in 2018 will be completed as we do not have road access to outriggers NW1, NW2 and NW3 yet. This will be done early 2019 as far as I understand.

Slide 2:
Second slide shows pipes, bending 90 degrees into the culvert close to main Eiscat antenna site.

Slide 3:
Last slide is a drone picture I got from Johan Svensson at Eiscat today. It was taken thursday last week, and as you can see, they have now cut and removed all trees on the main antenna site.

Best regards

Helge Stranden | Senior Advisor, ICT & HPC physical Infrastructure

Uninett Sigma2 - The Norwegian e-infrastructure for Research & Education

Uninett - The Norwegian Research & Education network

https://uninett.zoom.us/my/helge.stranden

+47 23 96 05 88 / ID: 516-646-7508

Mobile: +47 48 36 24 06

--
Lars Fischer - Strategy & Policy, NORDUnet
lars@nordu.net, +45 2288 1729, @lpfischer