On 29 Sep 2018, at 13:09, Börje Josefsson wrote:
I can confirm that we can build the ring without
Kaiseniemi. That site
will be done as a spoke from Kiruna anyway.
Thanks, BJ
And as of your question on cost etc from 2 weeks ago.
I can confirm
that
the SUNET fiber cost stated there is correct (but lacks the last
mile).
Thanks.
Also the equipment should be fine as long as
everything else (in .NO
and
.FI) is untouched. I suggest that we let Lars Lange sync the equipment
one final time after everybody has sent in their info.
Agreed. Also, for those who have not yet done so: please make sure Lars
Lange have updated KMZ files.
/Lars
—
Lars Fischer - Strategy & Policy, NORDUnet
<lars(a)nordu.net>, +45 2288 1729, @lpfischer