(resent; there was some list error so it was not processed correctly -
Lars)
Attached you can find a short status report from our pipe lay in
Skibotn, before the video meeting tomorrow.
Slide 1:
The first slide shows where we are right now, and you can see the
excavator close to outrigger W2. During this week everything that can be
done in 2018 will be completed as we do not have road access to
outriggers NW1, NW2 and NW3 yet. This will be done early 2019 as far as
I understand.
Slide 2:
Second slide shows pipes, bending 90 degrees into the culvert close to
main Eiscat antenna site.
Slide 3:
Last slide is a drone picture I got from Johan Svensson at Eiscat today.
It was taken thursday last week, and as you can see, they have now cut
and removed all trees on the main antenna site.
Best regards
Helge Stranden | Senior Advisor, ICT & HPC physical Infrastructure
--------------------------------------------------------------------------------------------------------
Uninett Sigma2 - The Norwegian e-infrastructure for Research & Education
Uninett - The Norwegian Research & Education network
----------------------------------------------------------
https://uninett.zoom.us/my/helge.stranden
+47 23 96 05 88 / ID: 516-646-7508
---------------------------------
Mobile: +47 48 36 24 06
--
--
Lars Fischer - Strategy & Policy, NORDUnet
<lars(a)nordu.net>, +45 2288 1729, @lpfischer